WINNER TOWER: gear for champions.
The WINNER Tower is progressing at an impressive pace, with 95% of the underground pile cup foundation casting completed. The slab on grade for the ground floor is 50% complete, and the erection of water tank walls in the underground floor is fully finished. Basement floor drainage has been completed 100%, and the erection of the lift shaft on the ground floor is also 100% done, along with the tower crane erection.
Work is actively ongoing, with de-shuttering for the last stage of the pile cap and strap beam, casting for the slab on grade and column GF-P01, steel work for Staircase-02, and MEP works. Additionally, site cleaning and material arrangement are underway to keep things moving smoothly.
With cutting-edge design and premium materials at the forefront, WINNER Tower is shaping up to be a true symbol of innovation and strength. Stay tuned as this iconic structure continues to rise!