V1TER: high-performance wellness.
The V1TER project continues its rapid progress, bringing the vision closer to completion with each stage. Concrete casting has now been fully completed up to the 22nd floor slab and roof slab, with only parapet works remaining on the upper roof. Block works have also reached 100% completion through the 22nd floor.
Plastering is completed up to the 19th floor, with work on the 20th floor now 70% complete. Podium floor painting is finalized, while primer and stucco works have been completed through the 19th floor, enhancing the building’s finish.
Tile flooring is progressing on the 19th floor and is now 50% done. False ceiling works are complete on the 13th floor, with suspension completed through to the 15th floor in both wet and dry areas.
Façade and external works continue with the balcony F-channel installed up to the 17th floor at 95% completion. Aluminum frame works are 95% complete up to the 10th floor, and 70% completed from the 11th to 17th floors. Joinery and glazing are completed in the mock-up units.MEP works are steadily progressing in parallel across all fronts. With superstructure works 100% complete and civil works at 70%, V1TER is shaping into a sophisticated and forward-looking residential tower. Stay tuned for more as the final stages unfold.