THE F1FTH TOWER: urban elegance redefined.

Construction of THE F1FTH Tower is advancing steadily, with floor slabs completed up to the 7th floor and columns and walls cast through to the 8th floor. Reinforcement for the 8th floor slab is now in progress, continuing the tower’s vertical rise.

Block work is done up to the 2nd floor and ongoing on the 3rd, while plastering and texture painting are fully completed across all five podium levels, giving form and finish to the structure’s base.

In Mock-Up Units 204 & 208, block and plastering are done, with MEP first fix in progress. Overall, MEP works continue smoothly alongside other site activities.

With 38% of the superstructure and 29% of civil works now complete, THE F1FTH Tower is moving confidently toward its vision. Stay tuned as progress continues to build.