Construction progress at RA1N is moving full steam ahead!
Concrete and block works are fully completed, and plaster and waterproofing are also 100% done. Tile works are nearing the finish line at 95%, while false ceiling installation stands strong at 85%. Aluminum frame work is almost complete at 95%, and painting works have reached 75%. Meanwhile, façade finishing works are progressing steadily at 70%, with landscaping and swimming pool works advancing at 30%.

With these milestones in place, RA1N is confidently progressing toward the next exciting chapter. With a sharp focus on quality and attention to detail, RA1N continues to evolve into an exceptional space. Stay tuned for more updates!