OZONE1: smart wellness community.
The OZONE1 project continues to gain vertical and technical momentum, with works across structure, finishes, and services reflecting consistent and coordinated execution.
Structural Progress has been significant, with floor slab casting now completed up to the 12th floor, marking a major milestone. Reinforcement works are actively ongoing for the columns, walls, and core wall between the 13th and 14th floors, driving the superstructure forward with precision.
Block work has reached the 6th floor, with ongoing activity on the 7th floor, contributing to a steady pace in vertical closure. Internally, plastering has been completed across all podiums and on the 2nd floor (11 flats), while surface preparation is progressing on the 1st and 3rd floors. On the exterior, texture painting is fully completed across all podium levels, and primer application has been finalized for the 2nd floor flats, advancing the project’s architectural expression.
Inside the Mock-Up Apartments (203, 204 & 207), the interior scope continues to take shape:
- Block work, plastering, and floor screed are complete.
- Tiling and false ceiling installation in both dry and wet areas are done.
- Painting works (primer and stucco) are completed, with the first coat in progress.
- Glass balustrade installation is underway, and kitchen cabinet works are progressing in Flat 203.
- Sanitary fixtures, including WC and shower sets, are fully installed, giving a preview of the final finish.
MEP installations are advancing in parallel with structural and interior works, supporting timely integration of essential systems.
With superstructure works now at 60% and civil works at 38%, OZONE1 is rising confidently toward its vision of delivering smart, stylish, and high-quality contemporary living.
Stay connected for more updates as we continue to bring OZONE1 to life, floor by floor.