OZONE1: smart wellness community.
The OZONE1 project continues to progress steadily, reflecting our commitment to creating a dynamic and contemporary living space. The floor slab casting has now been completed up to the 8th floor, with reinforcement works actively underway for columns and core walls between the 8th and 9th floors.
Block work has been completed through the 2nd floor, and is in progress on the 3rd and 4th floors, maintaining consistent vertical development. Plastering works have been finalized across all podium levels (up to Podium 4), while texture painting has also been completed up to the same level, enhancing the visual character of the façade.
Inside the Mock-Up Units (Apartments 203, 204 & 207), block and plastering works are complete, with floor screeding preparations in progress and MEP first fix installations finalized.
MEP activities continue in parallel across the site, in alignment with construction milestones. With superstructure works now at 53% and civil works at 35%, OZONE1 is shaping into a future-ready development marked by quality, functionality, and modern appeal.
Stay tuned as we continue building momentum and turning OZONE1 into reality.