OZONE1: smart wellness community.

The OZONE1 project continues to make impressive progress, staying true to its vision of creating a dynamic and modern space. We’re excited to share that the first-floor slab casting has been completed, with preparations for the second-floor slab casting now in progress. Block works have been completed on the 4th podium floor, and are currently ongoing at the podium’s high-level sections. Plastering has been completed on the 3rd podium floor, with work actively progressing on the 4th podium floor. Painting works have reached the fine coat stage on the 3rd podium floor, while texture application is underway on the 2nd podium floor and in preparation for the 4th podium. MEP works are also moving forward steadily in parallel with all other activities.

With superstructure works now at 25% and civil works at 20%, OZONE1 is steadily taking shape as a cutting-edge, functional space. Stay tuned for more updates as this exciting project continues to unfold!