OZONE1: smart wellness community.

The OZONE1 project continues to make impressive progress, staying true to its vision of creating a dynamic and modern space. We’re excited to announce that the podium floor slab casting has been completed, along with the successful casting of the swimming pool area and first floor slab. Preparations for the second-floor slab casting are currently underway. Block work has been completed on the ground, 1st, 2nd, and 3rd podium floors, with progress now moving onto the 4th podium floor. Plastering is complete on the 1st, 2nd, and 3rd podium floors, while painting works are in progress. MEP works are advancing smoothly in parallel with other tasks. With structure work now at 25% completion, OZONE1 is steadily taking shape as a cutting-edge, functional space. Stay tuned for more updates as this exciting project continues to unfold!