LUM1NAR Tower 1
Construction at Tower 1 continues to build upward with strong momentum. The Podium 1 and Podium 2 slabs, along with their vertical elements, are now fully completed at 100%, marking significant structural achievements. The Podium 3 slab has also been cast in full, while vertical elements at this level are now at 50% progress. Above, formwork for the Podium 4 slab has reached 50%, preparing the tower for its next stage of elevation. In parallel, MEP installations remain ongoing, maintaining early integration of building services with structural works.

LUM1NAR Tower 2
Tower 2 is making strong strides, with backfilling and tie beams fully completed at 100%. At the ground floor, both columns and the core wall are finalized, providing a solid foundation for the podium works above. The Podium 1 slab and vertical elements are 100% complete, while Podium 2 slab and vertical works have reached 70% progress, moving steadily toward full completion. MEP works continue in coordination with the advancing structure, ensuring smooth alignment across all disciplines.

LUM1NAR Tower 3
Initial works for Tower 3 are actively underway. Dewatering operations remain in progress, while excavation has reached 70% completion. In tandem, pile breaking is also 70% complete, steadily advancing the groundwork that will enable upcoming structural phases.

With synchronized efforts across all three towers, the LUM1NAR development is moving forward with precision and efficiency. Each stage reinforces the vision of delivering a landmark destination that exemplifies quality, planning, and progress. Stay connected as the towers continue their rise, shaping LUM1NAR into a defining presence on the skyline.