The 1WOOD project continues to demonstrate strong construction momentum and technical precision. With 100% of the concrete casting for the entire structure now completed, the superstructure has officially reached full completion — a major project milestone.
Block work has been fully completed up to the 11th floor, with 12th floor work currently in progress, reinforcing the building’s vertical development. Plastering is now 100% finished up to the 8th floor, with 50% of the 9th floor already completed, ensuring timely internal readiness.
Painting efforts are steadily advancing, with 90% of podium floor painting completed and 90% of primer painting (walls and ceilings) done up to the 8th floor, adding visual definition to the typical floors.
On the finishing front, tile flooring is nearing completion on the 7th floor (90%) in both dry and wet areas, and has now commenced on the 8th floor. False ceiling installation has reached 90% up to the 6th floor, with suspension works 80% done up to the 8th floor’s dry zones.
Joinery and glazing work in mockup flats remains complete, effectively previewing the aesthetic vision of 1WOOD. Meanwhile, glazing works across the building are actively progressing, bringing clarity and modernity to the façade.
MEP services are advancing in parallel, ensuring seamless integration and operational alignment. With superstructure works now at 100% and civil works reaching 70% completion, 1WOOD is transitioning confidently into the final stages of development.
Stay tuned as we elevate the 1WOOD vision into a reality marked by quality, design, and delivery.