1WOOD: nature-inspired homes.

The 1WOOD project is progressing right on track, with the casting of the 9th floor slab now completed and preparations for the 10th floor slab already in motion. Block work has been completed up to the 4th floor, with ongoing activity on the 5th and 6th floors, maintaining consistent forward momentum across levels.

Plastering works on the podium and 2nd floor are finished, while the 3rd and 4th floors are steadily advancing. Painting on the podium floors is fully complete, and the second floor has now entered the painting stage, contributing to the project’s evolving finish and feel.

MEP works are also progressing in parallel, ensuring that every detail aligns with our standards of precision and quality. With superstructure works now 70% complete and civil works at 35%, 1WOOD is shaping into a refined blend of modern function, aesthetic clarity, and sustainable intent.

Stay connected as we continue turning the 1WOOD vision into a built reality.The 1WOOD project is advancing confidently, with all typical floor slabs and the roof slab now fully cast. Block work is 90% complete up to the 10th floor, with the 11th floor underway, ensuring strong vertical progress.

Plastering has reached 90% completion up to the 6th floor, and is progressing on the 7th. Podium painting is 90% done, while painting up to the 6th floor has reached 70%, steadily shaping the project’s interior character.

Tile flooring is 40% complete on the 6th floor and now underway on the 7th. False ceiling works are 40% done up to the 5th floor, with suspension completed up to the 6th. Joinery and glazing are finished in the mockup flats, showcasing the design vision ahead.

MEP works continue in parallel, aligning with our standards of precision and coordination. With superstructure works now 90% complete and civil works at 50%, 1WOOD is rapidly transforming into a modern, refined, and sustainable development.

Stay connected as we bring the 1WOOD vision to life.