1WOOD: nature-inspired homes.
The 1WOOD project is progressing right on track, with the casting of the 9th floor slab now completed and preparations for the 10th floor slab already in motion. Block work has been completed up to the 4th floor, with ongoing activity on the 5th and 6th floors, maintaining consistent forward momentum across levels.
Plastering works on the podium and 2nd floor are finished, while the 3rd and 4th floors are steadily advancing. Painting on the podium floors is fully complete, and the second floor has now entered the painting stage, contributing to the project’s evolving finish and feel.
MEP works are also progressing in parallel, ensuring that every detail aligns with our standards of precision and quality. With superstructure works now 70% complete and civil works at 35%, 1WOOD is shaping into a refined blend of modern function, aesthetic clarity, and sustainable intent.
Stay connected as we continue turning the 1WOOD vision into a built reality.