KEY WORKS WERE UNDERTAKEN & COMPLETED on RA1N Project

Project update for today:

  • Steel reinforcement and post tension work at 24th floor slab is ongoing, will casted Monday
  • – Block work at 18th floor
  • – Block work at 17th floor
  • – Plaster work at 15th floor
  • – MEP work (AC ducting) at 7th floor
  • – Screed for corridor flooring at 6th floor
  • – Painting and protecting at Mockup 502