Construction at the RA1N project is active with continuous progress. Get the latest updates here:

  • Key works were undertaken & completed slab casting, block work and plaster are progressing well
  • 19th floor slab casted, block works on 15th floor, plaster works on 19th floor high-level map work was completed on floor 8
  • 10,500 cubic meters of concrete were poured