Construction update LUMINAR

LUM1NAR 1: future-forward real estate.

Construction on LUM1NAR Towers 1 & 2 continues to move forward with precision and momentum, keeping pace with the project schedule and reinforcing the development’s vision of excellence.

LUM1NAR Tower 1

A key structural milestone has been achieved with the completion of the Podium 1 columns and core walls at 100%. Deshuttering works are now underway at the ground floor, signaling readiness for vertical progression. Above, formwork for the Podium 2 slab is 50% complete, while steel reinforcement works have reached 30%, setting the stage for the upcoming concrete pours. Meanwhile, MEP installations remain in progress, ensuring early coordination of essential building services.

LUM1NAR Tower 2

Tower 2 is making substantial vertical gains, with ground floor columns and the core wall now fully completed. Block work has commenced at the ground floor, marking the start of internal construction activity. At Podium 1, beam fabrication is in progress, while steel reinforcement is actively underway on the ramp connecting the ground floor to Podium 1. In parallel, MEP works continue steadily, aligned with structural developments.

With synchronized construction efforts and well-coordinated MEP execution, LUM1NAR Towers 1 & 2 are progressing confidently toward their architectural promise. The project stands as a testament to meticulous planning and strong execution.

Stay connected as we continue to shape LUM1NAR into a landmark development, floor by floor.

Construction update WINNER TOWER

WINNER TOWER: gear for champions.

The W1NNER Tower continues its upward momentum, marking another significant phase in construction progress. The ground floor slab and columns have been successfully cast, reaching 100% completion, and the Podium 1 slab has also been fully completed — setting the stage for vertical development above podium level.

Steel reinforcement works for the Podium 1 columns and core wall are now actively in progress, shaping the core structure for the next levels. At the same time, MEP works are progressing in parallel, ensuring essential systems are well-aligned with structural timelines.

With major foundational elements behind us and superstructure activities ramping up, W1NNER Tower continues to embody precision, progress, and purposeful design. Stay tuned as this landmark development continues to rise and define its place on the skyline.

Construction update THE F1FTH TOWER

THE F1FTH TOWER: urban elegance redefined.

The THE F1FTH Tower continues its upward journey, with progress across structure, finishes, and services unfolding in seamless coordination. As the building ascends, every phase reflects a focused drive toward quality, design, and timely delivery.

On the structural front, the floor slab casting has reached the 12th floor, while the columns and walls through to the 13th floor have been successfully completed. Reinforcement for the 13th floor slab is now underway, advancing the superstructure’s vertical rhythm and preparing for the next level of elevation.

Simultaneously, block work is complete up to the 5th floor, and has now begun on the 6th, shaping the internal layout with increasing pace. Plastering works, previously completed across all five podium levels, are now extending upward and progressing on the 1st floor, while the texture finish on podium levels is fully complete, giving architectural definition to the base of the tower.

Inside the Mock-Up Units (204 & 208), progress showcases the evolving interior character of the project. Block and plastering works are done, with floor tiles and wall cladding completed, and false ceiling installations finalized. Aluminum framing and glass balustrade works are in motion, adding both safety and refinement, while MEP first fix installations have been fully wrapped up, setting the stage for final fit-outs.

Across the tower, MEP works continue in tandem with civil and structural activities, ensuring services are integrated early and efficiently.

With superstructure completion now at 42% and civil works at 31%, THE F1FTH Tower is building momentum on all fronts. The project is steadily transforming into a refined, modern development—floor by floor, detail by detail.

Stay with us as we shape this landmark into reality, guided by purpose, progress, and precision.

Construction update OZONE1

OZONE1: smart wellness community.

The OZONE1 project continues to gain vertical and technical momentum, with works across structure, finishes, and services reflecting consistent and coordinated execution.

Structural Progress has been significant, with floor slab casting now completed up to the 12th floor, marking a major milestone. Reinforcement works are actively ongoing for the columns, walls, and core wall between the 13th and 14th floors, driving the superstructure forward with precision.

Block work has reached the 6th floor, with ongoing activity on the 7th floor, contributing to a steady pace in vertical closure. Internally, plastering has been completed across all podiums and on the 2nd floor (11 flats), while surface preparation is progressing on the 1st and 3rd floors. On the exterior, texture painting is fully completed across all podium levels, and primer application has been finalized for the 2nd floor flats, advancing the project’s architectural expression.

Inside the Mock-Up Apartments (203, 204 & 207), the interior scope continues to take shape:

  • Block work, plastering, and floor screed are complete.
  • Tiling and false ceiling installation in both dry and wet areas are done.
  • Painting works (primer and stucco) are completed, with the first coat in progress.
  • Glass balustrade installation is underway, and kitchen cabinet works are progressing in Flat 203.
  • Sanitary fixtures, including WC and shower sets, are fully installed, giving a preview of the final finish.

MEP installations are advancing in parallel with structural and interior works, supporting timely integration of essential systems.

With superstructure works now at 60% and civil works at 38%, OZONE1 is rising confidently toward its vision of delivering smart, stylish, and high-quality contemporary living.

Stay connected for more updates as we continue to bring OZONE1 to life, floor by floor.

Construction update 1WOOD

1WOOD: nature-inspired homes.

The 1WOOD project continues to demonstrate strong construction momentum and technical precision. With 100% of the concrete casting for the entire structure now completed, the superstructure has officially reached full completion — a major project milestone.

Block work has been fully completed up to the 11th floor, with 12th floor work currently in progress, reinforcing the building’s vertical development. Plastering is now 100% finished up to the 8th floor, with 50% of the 9th floor already completed, ensuring timely internal readiness.

Painting efforts are steadily advancing, with 90% of podium floor painting completed and 90% of primer painting (walls and ceilings) done up to the 8th floor, adding visual definition to the typical floors.

On the finishing front, tile flooring is nearing completion on the 7th floor (90%) in both dry and wet areas, and has now commenced on the 8th floor. False ceiling installation has reached 90% up to the 6th floor, with suspension works 80% done up to the 8th floor’s dry zones.

Joinery and glazing work in mockup flats remains complete, effectively previewing the aesthetic vision of 1WOOD. Meanwhile, glazing works across the building are actively progressing, bringing clarity and modernity to the façade.

MEP services are advancing in parallel, ensuring seamless integration and operational alignment. With superstructure works now at 100% and civil works reaching 70% completion, 1WOOD is transitioning confidently into the final stages of development.

Stay tuned as we elevate the 1WOOD vision into a reality marked by quality, design, and delivery.

Construction update V1TER

V1TER: high-performance wellness.

The V1TER project continues its rapid progress, bringing the vision closer to completion with each stage. Concrete casting has now been fully completed up to the 22nd floor slab and roof slab, with only parapet works remaining on the upper roof. Block works have also reached 100% completion through the 22nd floor.

Plastering is completed up to the 19th floor, with work on the 20th floor now 70% complete. Podium floor painting is finalized, while primer and stucco works have been completed through the 19th floor, enhancing the building’s finish.

Tile flooring is progressing on the 19th floor and is now 50% done. False ceiling works are complete on the 13th floor, with suspension completed through to the 15th floor in both wet and dry areas.

Façade and external works continue with the balcony F-channel installed up to the 17th floor at 95% completion. Aluminum frame works are 95% complete up to the 10th floor, and 70% completed from the 11th to 17th floors. Joinery and glazing are completed in the mock-up units.

MEP works are steadily progressing in parallel across all fronts. With superstructure works 100% complete and civil works at 70%, V1TER is shaping into a sophisticated and forward-looking residential tower. Stay tuned for more as the final stages unfold.

Construction update RA1N

RA1N: sustainable luxury living

RA1N: sustainable luxury living.

Construction progress at RA1N continues at a steady and promising pace! Concrete, block, plaster, and waterproofing works are now fully completed, marking the close of major structural activities. Tile work has reached 98%, and false ceiling installation is also at 98%, signaling near-final interior finishes.

Aluminum frame works are 97% complete, while painting works have advanced to 88%. Façade finishing stands at 85%, adding refined character to the building’s exterior. Landscaping and swimming pool works are now 45% complete, introducing the early touches of outdoor living and amenity zones.With every detail shaping up beautifully, RA1N is approaching its final form — a carefully crafted, high-quality development. Stay tuned for more updates as the project enters its final stretch.

Construction update 1WOOD

1WOOD: nature-inspired homes.

The 1WOOD project is progressing right on track, with the casting of the 9th floor slab now completed and preparations for the 10th floor slab already in motion. Block work has been completed up to the 4th floor, with ongoing activity on the 5th and 6th floors, maintaining consistent forward momentum across levels.

Plastering works on the podium and 2nd floor are finished, while the 3rd and 4th floors are steadily advancing. Painting on the podium floors is fully complete, and the second floor has now entered the painting stage, contributing to the project’s evolving finish and feel.

MEP works are also progressing in parallel, ensuring that every detail aligns with our standards of precision and quality. With superstructure works now 70% complete and civil works at 35%, 1WOOD is shaping into a refined blend of modern function, aesthetic clarity, and sustainable intent.

Stay connected as we continue turning the 1WOOD vision into a built reality.The 1WOOD project is advancing confidently, with all typical floor slabs and the roof slab now fully cast. Block work is 90% complete up to the 10th floor, with the 11th floor underway, ensuring strong vertical progress.

Plastering has reached 90% completion up to the 6th floor, and is progressing on the 7th. Podium painting is 90% done, while painting up to the 6th floor has reached 70%, steadily shaping the project’s interior character.

Tile flooring is 40% complete on the 6th floor and now underway on the 7th. False ceiling works are 40% done up to the 5th floor, with suspension completed up to the 6th. Joinery and glazing are finished in the mockup flats, showcasing the design vision ahead.

MEP works continue in parallel, aligning with our standards of precision and coordination. With superstructure works now 90% complete and civil works at 50%, 1WOOD is rapidly transforming into a modern, refined, and sustainable development.

Stay connected as we bring the 1WOOD vision to life.

Construction update V1TER

V1TER: high-performance wellness.

The V1TER project continues its rapid progress, bringing the vision closer to completion with each stage. Concrete casting has now been fully completed up to the 22nd floor slab and roof slab, with only parapet works remaining on the upper roof. Block works have also reached 100% completion through the 22nd floor.

Plastering is completed up to the 19th floor, with work on the 20th floor now 70% complete. Podium floor painting is finalized, while primer and stucco works have been completed through the 19th floor, enhancing the building’s finish.

Tile flooring is progressing on the 19th floor and is now 50% done. False ceiling works are complete on the 13th floor, with suspension completed through to the 15th floor in both wet and dry areas.

Façade and external works continue with the balcony F-channel installed up to the 17th floor at 95% completion. Aluminum frame works are 95% complete up to the 10th floor, and 70% completed from the 11th to 17th floors. Joinery and glazing are completed in the mock-up units.MEP works are steadily progressing in parallel across all fronts. With superstructure works 100% complete and civil works at 70%, V1TER is shaping into a sophisticated and forward-looking residential tower. Stay tuned for more as the final stages unfold.