The construction of the project V1TER Residente is ongoing in accordance with the agreed plan.

As of today, the following progress has been made:

  • under-ground (sub-structural) works 
  • piling and shoring has been completed 100% 
  • excavation works has been completed 100% 
  • pile caps works 50% completed 

Completion of construction: 3rd quarter of 2025