The V1TER project is progressing and remains on track with the original timeline. 

KEY WORKS WERE UNDERTAKEN & COMPLETED on V1TER Project: 

  • All ground floor columns and core walls has been completed 
  • Backfilling works up to ground 
  • Level works has been completed 
  • 1st podium slab shuttering and reinforcement works is in progress 
  • 2,800 cubic meters of concrete was poured