KEY WORKS WERE UNDERTAKEN & COMPLETED on RA1N Project
Project update for today:
- Steel reinforcement and post tension work at 24th floor slab is ongoing, will casted Monday
- – Block work at 18th floor
- – Block work at 17th floor
- – Plaster work at 15th floor
- – MEP work (AC ducting) at 7th floor
- – Screed for corridor flooring at 6th floor
- – Painting and protecting at Mockup 502