The 1WOOD project has ongoing construction processes. 7% of the overall work assigned for this project is successfully completed, including the major tasks:
- Sub-Structural works (underground works)
- Pile works has been completed (total piles 100)
- deep foundations (piling and shoring) works has been completed
- excavations works: under progress 30% has been completed
- Dewatering works under progress
- Piles head breaking works has been started
Completion of construction: 3rd quarter of 2025